The housing secretary has called on house builder Galliard to honour its promise to reimburse residents decanted from an unsafe block for their temporary accommodation costs.
In a scathing letter published on X yesterday (Tuesday 24 November), Angela Rayner said she had significant concerns about how Galliard had handled the Royal Gateway development, recently evacuated due to major structural issues related to the ‘transfer slab’.
Ms Rayner said she has ordered officials to begin an urgent review of Galliard buildings that the firm has assessed as not requiring any work.
She wrote: “My officials suggested you needed help with temporary accommodation on 4 November, but you did not appoint anyone until 17 November, nearly two weeks later.
“This has left residents to foot the bill for temporary accommodation. Some have such little faith in your promise of reimbursement that they have chosen to remain in or even return to buildings with structural defects that pose an imminent risk to life.”
Inside Housing covered the initial delay on 13 November, after a number of residents were still living in the blocks with an “imminent risk to life” on the east London development, while others have spent thousands of pounds on temporary housing, three weeks after they were ordered to evacuate.
Four days later, a letter sent from the managing agent revealed gas and water utilities are to be switched off for residents who returned to live in the blocks.
The housing secretary continued: “I wonder if Galliard would have been so slow to do the right thing if your chief executive still owned a penthouse flat at Caxton Works.”
Ms Rayner was referring to multiple reports over the weekend that revealed the boss of Galliard had to deny knowing about the building’s structural problems before he sold his penthouse flat in the block for £720,000 in May 2026.
A few days before the news of the flat sale broke, Inside Housing revealed that a director at Galliard said it would be “absolutely foolhardy and ridiculous” to say “there’s no threat to life” after viewing large cracks in a transfer slab at the property.
Ms Rayner added: “You must honour your promises without delay, or knowingly risk a further, dangerous deterioration of trust.
“In fact, you should feel morally bound to go further: as long as residents are unable to return home, they will have financial and practical needs that I expect Galliard to meet. Anyone considering buying one of your homes in future will be watching how you act now, and so will I.
“Galliard’s conduct has done nothing to improve its reputation. I am aware that you were among the final companies to sign the contract to remediate your own buildings.
“The attitude that demonstrated – putting finance before fairness – seems sadly still too prevalent in your company today.”
Galliard Homes signed the government’s post-Grenfell remediation contract over three weeks after the deadline passed on 5 April 2023.
Inside Housing reported last month that remediation work has not started on more than 1,000 buildings in England with life-critical fire safety defects that developers are responsible for resolving, and a key July deadline has already been missed.
In response to Ms Rayner’s letter, the right to manage (RTM) companies of Royal Gateway, said: “For over four weeks, with the support of Prime Property Management and the legal assistance of Ross Wilson from Spencer West, the RTM have engaged with all interested parties, proposed solutions and posed many questions – most of which sadly remain unanswered, to devise a way forward to swiftly access adequate temporary rehousing, corroborate the technical findings on Slab 1 and Slab 2, and collaboratively define a timeline to bring back safety for residents to return to their homes while remediation works are implemented. As of today these plans remain an aspiration.
“We call on Galliard to turn over a new leaf and put an end to our despair by providing tangible and concerted solutions for all people affected by the structural faults that our technical experts have found back in October.”
A Galliard Homes spokesperson said: “Galliard has already put temporary accommodation and reimbursement arrangements in place for Royal Gateway residents. We share the secretary of state’s determination that residents receive the support they need, and our focus is on getting that support to them as quickly as possible.
“ICAB [Insurance Claims Accommodation Bureau] is arranging like for like temporary accommodation within the area, with Galliard paying the accommodation costs directly. Residents using the service do not have to pay upfront or claim those costs back. Each household’s circumstances and accommodation needs are considered individually.
“Our commitment to reimburse reasonable relocation and temporary accommodation costs was first announced on 5 November. The offer covers costs incurred from the relevant evacuation dates and has since been extended up to and including 17 December 2026, unless residents can return home sooner.
“We have a dedicated building safety team that works closely with MHCLG, the Building Safety Regulator, freeholders, managing agents and leaseholders to identify solutions and support those affected by any issues related to building safety.
“This support is provided without admission of liability and without prejudice to Galliard’s position, including any rights against third parties.”
The End Our Cladding Sandal campaign group said: “The urgent review of Galliard’s buildings is welcome, but must go much further.
“There must be independent audits of all developers’ assessments where no remediation is deemed necessary, and of the scope of works where remediation is deemed necessary.
“Developers cannot keep marking their own homework. Strong words from ministers must be matched by decisive action from their department.
“The remediation bill is an opportunity to address these systemic failures. This is a start. There is much, much more to do.”